HENDERSON, Ky. (Nov. 13, 2026) – A southbound Twin Bridge closure is scheduled for Friday night.
Repairs to the U.S. 41 Twin Bridges are entering their final stage, beginning with changes to the existing traffic pattern scheduled at 7:30 p.m. Friday.
At 6 p.m., the crossovers currently being used to divert southbound traffic onto the northbound bridge will close, temporarily restricting all southbound traffic to one lane on the southbound bridge.
Once that transition is complete, the northbound fast lane will close, and crews will begin installing pavement markers along the centerline of the northbound bridge.
At approximately 7:30 p.m., the crossovers will reopen, and the southbound bridge will close completely. All traffic crossing the Twin Bridges will be directed onto the northbound bridge, where two 15-foot lanes will accommodate traffic in both directions.
The final repairs included in this project are scheduled to begin shortly after the closure and are expected to be completed before Saturday morning. Once the repairs are finished, crews will close the crossovers and reopen both lanes of the southbound bridge.
Following the transition, northbound traffic will be restricted to two 10-foot lanes until crews can restripe the northbound bridge. That work is scheduled to begin at 9 a.m. Sunday, Nov. 15, but will depend on temperatures reaching the minimum required for pavement marking operations.